Co-op Centre Project

Share Co-op Centre Project on Facebook Share Co-op Centre Project on Twitter Share Co-op Centre Project on Linkedin Email Co-op Centre Project link

In fall of 2021 the City applied for a grant under the Investing in Canada Infrastructure Program (ICIP). This application was to construct not just a replacement for the Arena that burned down in the summer of 2021, but to develop a multi-purpose facility that could provide enhanced programming and services to the community and surrounding region. We received official grant approval in fall of 2022 and are moving forward with this once in a generation project.

The Design-Build contract was awarded to Quorex Construction on April 24, 2023.

Council approved including the Field House in the scope of the

In fall of 2021 the City applied for a grant under the Investing in Canada Infrastructure Program (ICIP). This application was to construct not just a replacement for the Arena that burned down in the summer of 2021, but to develop a multi-purpose facility that could provide enhanced programming and services to the community and surrounding region. We received official grant approval in fall of 2022 and are moving forward with this once in a generation project.

The Design-Build contract was awarded to Quorex Construction on April 24, 2023.

Council approved including the Field House in the scope of the project (adding an extra $9.5 million to the overall project budget) on May 8, 2023.

Construction is now underway!

The goal of the project is substantial completion of the arena by February 2025, and the rest of the facility by March 31, 2025.

Subscribe to this project page by clicking the subscribe button to the right to receive updates and notices on existing and future engagement for this project!


This project is funded in part by:


Q&A

Questions about this project? Ask them here! 

You need to be signed in to add your question.

  • Share FYI.... I see in the recent Meadow Lake update mailout (Second page) for the recreation center on May 8th council approved 9.5 million for the field house. We failed to mention in this update that the RM contributed money. We do mention their contribution it in this forum. on Facebook Share FYI.... I see in the recent Meadow Lake update mailout (Second page) for the recreation center on May 8th council approved 9.5 million for the field house. We failed to mention in this update that the RM contributed money. We do mention their contribution it in this forum. on Twitter Share FYI.... I see in the recent Meadow Lake update mailout (Second page) for the recreation center on May 8th council approved 9.5 million for the field house. We failed to mention in this update that the RM contributed money. We do mention their contribution it in this forum. on Linkedin Email FYI.... I see in the recent Meadow Lake update mailout (Second page) for the recreation center on May 8th council approved 9.5 million for the field house. We failed to mention in this update that the RM contributed money. We do mention their contribution it in this forum. link

    FYI.... I see in the recent Meadow Lake update mailout (Second page) for the recreation center on May 8th council approved 9.5 million for the field house. We failed to mention in this update that the RM contributed money. We do mention their contribution it in this forum.

    Councilor Read asked over 1 year ago

    Thank you for the clarification Councillor Read. 